NDERE CENTRE
MIXED USE CULTURAL FACILITY
PROJECT FACTS
| Location: |
Kampala, Uganda |
| Client: |
Ndere Foundation |
| Services provided: |
Architecture, Project Management, Structural Engineering |
| Other Consultants: |
Stephen Wyard (consulting Architect) YMR (Cost consultant-Phase I) |
| Contractor: |
Hacom |
| Value: |
US$ 1,280,000 |
| Completion: |
October 2007 |
| Project status: |
Completed |
DESCRIPTION
The design and supervision of a mixed used cultural facility set in open parkland and utilising locally available materials. Developed over 3 phases - Phase I includes a reception building, cafe, open-air amphitheatre and staff facilities; Phase II provides a 400 person theatre. Phase III provides further staff accommodation and offices.